City of York Council (Logo)

Meeting:

Place Scrutiny

Meeting date:

22/09/2025

Report of:

Dave Atkinson – Director of Environmental and Regulatory Services

Portfolio of:

Executive Member for the Environment and Climate Emergency (Cllr J Kent)

 

Parks Investment Fund – scheme approval

Summary

 

1.           This report seeks feedback from the Committee on the recommended allocation of the park’s investment fund.  Feedback from the Committee will be incorporated into the report scheduled for consideration by the Executive on 7th October 2025.

 

Background

 

2.           Following the previous reports on the investment criteria to the Place Scrutiny Committee on 24th June 2025 and the Executive on 15th July 2025 officers have applied the weighted approach to nearly 60 Council play areas, parks, and smaller green spaces. As some sites have multiple issues this results in over 70 assessed sites and schemes.

 

3.           Officers have also undertaken a review of developer Section 106 contributions that the council holds for parks and open space infrastructure.  As part of this programme of work

 

·        Where S106 Agreements allow, funding will be pooled to enhance this programme

·        Where funding is stand alone, projects will be delivered in parallel with the core programme of work.

 

4.           This exercise, along with 3rd party funding means that the core programme budget is now close to £750k. Of which £602k is earmarked for the schemes, £85k for staff costs and £62k held in reserve as a contingency.  

 

5.           Where the S106 money is committed to 3rd parties as part of the planning agreements it will be distributed in parallel with this programme of work. This takes the overall budget to circa £925k.

 

6.           The views of Scrutiny Committee are now being sought on how the weighting has been applied and the resulting list of priority schemes recommended for implementation. 

 

Options

 

7.           Members have the option to

 

A.  Agree the weighting detailed below in Paragraphs 8 to 10 and resulting schemes detailed in Paragraph 11.

B.  Suggest an alternative weighting to be used to allocate the available funds.

 

Weighting and methodology

 

8.           The schemes detailed Paragraph 11 have been compiled using a weighted approach to reflect the agreed order of theme priority. 

 

 Sites with higher IMD

Replacing play equipment over 20 years old

Key infrastructure

 

Then equal weight to

 

Green Flag award

Availability of external funds

 

9.           Each theme is scored out of a 100% with 100 marks been awarded to the highest score within each theme. Lower scores are than awarded marks based on a % of the highest mark possible within each theme. The resulting score is then given an added weighting to reflect the priority of that theme.

 

Indices of Multiple Deprivation (IMD) Scores range from 25.70 (100%) to 4.69 (19%).  The higher the score the higher the level of deprivation.  Weighting x 4

 

Investment into play areas. Scores range from 20 (100%) to 4 (20%).  The higher the score the older the age of equipment in 5-year bands, 34 years being the age of the oldest equipment identified. The age of play equipment has been established via manufactures tags, photographic and tender records held by the service and Google Street View and noted in Annex 2. Weighting x 3

 

Key infrastructure. Scores range from 15 (100%) to 3 (20%).  The higher the score the greater the need for a rebuild through to minor works. Weighting x 2

 

Support the expansion and retention of Green Flag Award standard.  A single score of 10 (100%) has been allocated. Weighting x 1

 

Projects which have or have the potential for 3rd party funding contributions. Scores range from 10 (100%) to 2 (20%).  The higher the score the greater the contribution defined as external or ward funding. Weighting x 1

 

10.        This can be summarised as follows

 

Theme

 

IMD score

Play area equipment scores

Infrastructure scores

Green Flag score

3rd party £’s scores

Numerical value used in annex 2 *

 

 

 

 

 

 

25.70

20

15

10

10

100

 

 

 

 

 

90

20.06

16

12

 

 

80

 

 

 

 

 

70

15.04

12

9

 

 

60

 

 

 

 

5

50

10.03

8

6

 

 

40

 

 

 

 

 

30

5.01

4

3

 

 

20

 

 

 

 

2

10

 

*to which weighting is then applied

 

Outcome

 

11.        A site-by-site assessment is detailed in Annex 2 including the indicative total cost and cost to the Parks fund.  Those schemes recommended for investment and further investigation are listed in Annex 1, and are summarised as

 

Recommended for investment

 

Annex 2 ref no.

Site

Scheme featues

Total Marks

Ward

1

 

 

Chesney's Field play area - junior

new equipment, seating, new linking path

760

 

 

Westfield

2

Hull Road Park main play area

 

 

New items of equipment and accessible seating, safety surfacing

731

 

 

 

 

Hull Road

3

 

 

Chesney's Field play area - senior

New safety surfacing

 

680

 

 

Westfield

4

 

 

 

 

Crombie Avenue play area and adjoining games court

Near 100% rebuild of play area with new entrances. Surface work to games court

669

 

 

 

 

Clifton

5

 

 

Ashton Avenue play area (junior)

play equipment, access improvements

648

 

 

Clifton

8

 

 

Acomb Green play area

 

high footfall and wear, replacement steps required

603

 

 

Westfield

9

 

 

Rowntree Park play area

replacement of 6m high pyramid climber

593

 

 

Micklegate

10

 

 

Brailsford Crescent play area - Junior

Complete replacement of old equipment

575

 

 

Rawcliffe and Clifton Without

14

 

 

 

Hull Road Park - footpath by beck

Rebuild footpath

 

 

 

551

Hull Road

15

 

 

 

Glen Gardens Basketball Court

 

court surface is worn out, perimeter fencing needs replacing

547

 

 

 

Heworth

16

 

 

Batchelor Hill - Tenant Rd entrance

rebuild steps, install handrail

 

534

 

 

Westfield

18

 

 

 

Cemetery Road play area

 

Replacement of old remaining play equipment. Landscaping work

527

Fishergate

19

 

 

 

 

Bell Farm / Byland Avenue open space and play area

Create more coherent open space

 

 

522

 

 

 

 

Heworth

21

 

 

Hull Road Park - Lions Head area

Renew up of bow top fence, new handrails

511

 

 

Hull Road

22

 

 

 

Hull Road Park - Millfield Avenue boundary

Renew perimeter railings and new gate

 

511

 

 

 

Hull Road

23

 

 

 

Hull Road Park - Millfield Avenue footpath

Upgrade rough path to improve accessibility

 

511

 

 

 

Hull Road

26

 

 

 

Rowntree Park basketball court

New surface and boundary fence

 

 

476

 

 

 

Micklegate

29

 

 

 

 

 

Viking Road play area

 

 

 

 

Reclad bridge mound, renewal of few remaining old play equipment items, access improvements

455

Acomb

30

 

 

Cornlands Rd open spaces/ play area

New surfaced path across site with link to play area

454

Westfield

 

Nine of the above projects are at sites which serve more than one ward, some serve multiple wards. Column E in the Annex 1 identifies such sites.


 

 

Recommended for further investigation - into the practicality and cost.

 

Annex 2 ref no.

Site

Scheme summary

Score

Ward

13

 

 

 

Clarence Gardens pavilion

 

internal remodelling to allow community use / refreshments to be provided

559

Guildhall

20

 

 

Hull Road Park pavilion

 

Building needs modernising to expand use

511

Hull Road

25

 

 

 

Acomb Green - path access

 

Possible pedestrian ramp onto Green adjacent to bus stop

483

Acomb

28

 

 

 

 

Monkbridge Gardens

 

 

 

Rebuild access from Heworth Green, possible extension of tarmac path network

459

 

 

 

 

Heworth

38

 

 

 

 

Arran Place (King George V Playing Field)

New accessible route from / to Fossway

 

 

381

 

 

 

 

Heworth

 

12.        Where a site is known to be in good order and / or there is other funding available to rectify the issue, such sites have not been put forward even though they may score relatively high. 

 

Implications

 

13.        The implications are as follows:

 

·                    Financial, there are 19 schemes recommended in the first tranche which will receive funding from the Park Improvement Fund. The projected total cost is £687.5k including the project officer, leaving a contingency of £62.4k.  This is funded from £500k parks fund, specific and general 106 funds and 3rd party contributions.

·                    Human Resources (HR) The additional resource referred to in paragraph 29 to deliver this programme has been established and resourced in accordance with council policy. There are no other HR implications contained within this report.

·                    Legal the Council does not have a statutory duty to maintain parks.  However, the Council does have a duty of care to ensure the safety of public play areas and has a statutory duty under the Highways Act 1980 to maintain footpaths, and certain bridges, in a safe condition and fit for the type of traffic which is ordinarily expected to use it.  Under the War Memorials (Local Authorities’ Powers) Act 1923, the Council has the power, but not a duty, to maintain, repair and protect war memorials within its district The Councils policy approach to the management of parks should take into account all relevant considerations, as set out in this report. There is a growing body of case law which emphasises the importance of public bodies taking proportionate steps to combat climate change.

·                    Procurement.  Whilst there are no direct procurement implications relating this report itself, procurement will be a main tool used to deliver some of works if this report is approved. Future procurements for all works and/or services must be procured via a compliant, open, transparent, and fair process in accordance with the council’s Contract Procedure Rules and where applicable, the Procurement Act 2023. Further advice regarding the procurement process and development of procurement strategies must be sought from the Commercial Procurement team

·                    Health and Wellbeing As highlighted earlier in this report, well maintained parks and play infrastructure support physical activity, but also encourage social interaction and community engagement, all of which are beneficial for health. Prioritising funding for open spaces and play areas for those living in less affluent areas is welcome. We would also encourage development of these areas to take into account local need and views of residents including children moving forward as evidence suggests this is key to maximising use of such spaces. Finally, we urge consideration to be given to groups currently less likely to access, or facing barriers to accessing, the city’s open spaces and play areas such as disabled people or people from BME backgrounds.

·                    Environment and Climate action Enhancement of the city’s parks and green spaces can make an important contribution to tackling the challenges of climate change. The York Climate Change Strategy sets objectives for increased tree planting, increased carbon storage and sustainable land management. These objectives should be considered in the assessment of potential investment. Capital works have the potential to increase carbon emissions, and these should be mitigated and minimised wherever possible. Opportunities for biodiversity enhancement and climate adaptation could be considered as part of the assessment for potential investment.

·                    Affordability, Investment in green spaces and play areas supports activities which are free at the point of participation.

·                    Equalities and Human Rights, An Equalities Impact Assessment (EIA) is not required at this stage but will be required for the proposed work package to be presented later to Members.  Specific comments on the proposed way forward are contained within the main body of the report.

·                    Data Protection and Privacy The completion of data protection impact assessment (DPIA) screening questions evidenced there would be no processing of personal data, special categories of personal data or criminal offence data processed, so there is no requirement to complete a DPIA.

·                    Communications Local engagement in – and understanding of - this work will help the council to deliver this objective with the support of people in the areas affected. It is part of a wider story of support for communities across the city and information about this investment will be presented within the context of the range of activities making a difference on the ground. This will help council to explain how the different strands of work, including this investment, work together for the places where they live and work.

·                    Economy, None.

 

Next Steps

 

14.        Several schemes require input and consultation from users, communities, ward councillors, and specialist advisers before they can start, others can start to be delivered almost immediately. Once the Executive has approved the report briefings will be arranged for Councillors in those wards affected.

 


 

Risk Management

 

15.        There are no risks with this decision; the report will inform the planned report to the Councils Executive on 7th October 2025 where any risks will be reported.

 

Wards Impacted

 

16.        Those wards which are impacted are listed in paragraph 11, and in Annex 1 and 2.

 

Recommendations

 

17.        Members are asked to

 

Comment on the weighted approach detailed in Paragraphs 8 to 10 and the resulting priority schemes

 

Reason: to inform the Executives decision making

 

Contact details

 

For further information please contact the authors of this Report.

 


 

Contact Details

 

Author:

 

Chief Officer Responsible for the report:

Ian Hoult

Head of Environment Environmental Services

07923 206042

 

Dave Meigh

Operations Manager Public Realm

07923 217442

Dave Atkinson

Director of Environment & Regulatory Services

 

Report Approved

X

Date

10/09/2025

 

 

Background Papers

14 New Lane

Meeting of the Executive Member for Finance, Performance, Major Projects, Human Rights, Equality and Inclusion the Environment and Climate Emergency 16th January

https://democracy.york.gov.uk/ieListDocuments.aspx?CId=1060&MId=14518

Budget Council 27th February 2025

https://democracy.york.gov.uk/ieListDocuments.aspx?CId=331&MId=15004

Meeting of the Executive Member for the Environment and Climate Emergency 29th April 2025

https://democracy.york.gov.uk/ieListDocuments.aspx?CId=870&MId=14599

Meeting of the Place Scrutiny Committee 24th June 2025

https://democracy.york.gov.uk/ieListDocuments.aspx?CId=1122&MId=15314

Meeting of the Executive 17th July 2025

https://democracy.york.gov.uk/ieListDocuments.aspx?CId=733&MId=15173

Annexes

Annex 1 – Sites recommended for investment and further investigation

Annex 2 - Site Scores

Abbreviations IMD - Indices of Multiple Deprivation